Current report no. 5/2026 (09:09 a.m.)

Subject:
Execution of a significant contract with a value of PLN 65.6 million for the design and construction of a complete thermal energy storage (TES) installation and pumping station at EC4 in Łódź

Legal basis:
Article 17(1) of the Market Abuse Regulation (MAR) – inside information

Report content:
The Management Board of ERBUD S.A. (the “Issuer”) announces that on 16 February 2026 it entered into a significant contract for the design and construction of a complete thermal energy storage (TES) installation and pumping station at EC4 in Łódź, on the following terms:

  1. Date of execution: 16 February 2026
  2. Investor (full name and registered office address): Veolia Energia Łódź S.A., ul. J. Andrzejewskiej 5, 92-550 Łódź
  3. Contract value (net): PLN 65,623,440.00 + VAT
  4. Subject of the contract: Design and construction of a complete thermal energy storage (TES) installation and pumping station at EC4 in Łódź
  5. Place of execution: Łódź
  6. Completion deadlines: From the date of execution of the contract until 16 August 2027
  7. Payment terms: 30-day payment term
  8. Performance bond (amount, validity period): 10% of the gross contract value
  9. Defects liability bond (amount, validity period): 3% of the gross contract value
  10. Other guarantees (type, amount, validity period): In accordance with market standards; the standard warranty period for construction works is 60 months.
  11. Contractual penalties: Penalties are in line with market standards for contracts of this type. The total amount of contractual penalties may not exceed 20% of the net contract value.
  12. Additional information: The contract will be executed by the Toruń branch.